Final Stage of ZIPPE Batch House Erection for Vetropack in Italy

Cladding of Zippe Batch House in Boffalora (Milano) completed

In 2022, ZIPPE started the erection of the batch house for the Swiss glass group Vetropack in Boffalora. In the meantime the silos have been lifted in and the assembly of the equipment has been completed. Currently, test runs of the batch plant are in full progress.

The order was processed by ZIPPE on a turn-key basis. The batch plant is due to supply two melting furnaces. Two cullet return systems were also supplied by ZIPPE. All parties concerned are very pleased with the progress of the project and the plant can go into operation in the next few weeks.

www.zippe.de

Image: 
Cladding of Zippe Batch House in Boffalora (Milano) completed
Published: 
20/04/2023